G4S today published the findings of a PwC review into the London Olympic and Paralympic Games security contract with the company.

"The monitoring and tracking of the security workforce, management information and the project management framework and practices were ineffective to address the scale, complexities and dependencies of the Olympic contract. Together this caused the failure of the company to deliver the contract requirements in full and resulted in the identification of the key problems at a very late stage."

What conclusions would AccountingWEB members draw from PwC’s report into the security failings of G4S during the Olympics?

What kind of management information would the board have sight of? What remedial advice would you recommended?

Comments
There are 11 comments. Login or register to view them.

No real penalty

ShirleyM |
ShirleyM's picture

Who paid PWC's fees for this?

bernard michael |

i have some sympathy for G4S

carnmores |
carnmores's picture

G4S

ShirleyM |
ShirleyM's picture

well we will disagree on this

carnmores |
carnmores's picture

So locog (with limited experience)

justsotax |

Extension to contracts in Afghanistan ...

JC |

and why should they be

carnmores |
carnmores's picture

Security is a market like any other ...

JC |

On a purely personal note G4S

bernard michael |

OK

carnmores |
carnmores's picture